Abstract

Power system reliability is affected by the reliability of its sub-systems, including generator reliability. The reliability of a power plant can be seen, among others, based on the LOLE (Loss of Load Expectation) index. Processing and calculating data using excel or matlab will take a lot of time and effort.  This is unfavorable for system evaluation which is a routine activity. The contribution of this research is to create an easy data processing method with a user-friendly display using Java programming-based Visual Studio. The research data uses generator operating data in 2018 and 2019 Hydroelectric Power Plant Ir. H. Djuanda. Calculations using visual studio have been validated with calculations using Excel. LOLE calculation results in 2018 was 0.17356748092842464 days/year and for 2019 it produced a LOLE of 0.006204969593183424 days/year. The results obtained did not exceed the PLN standard, namely 1 days/year, in other words, in 2018 and 2019 Hydroelectric Power Plant Ir. H. Djuanda has a good level of reliability.

References

D. Marsudi, Operasi Sistem Tenaga Listrik, 2 ed. Yogyakarta: Graha Ilmu, 2006.

O. H. Abdalla, “Security and Reliability Criteria For Electricity Generation and Transmission System Planning,” Journal of the Egyptian Society of Engineers, vol. 61, no. 1, pp. 3–10, 2022, https://doi.org/10.21608/egsen.2022.247103.

A. Senen and R. Z. Akbar, “Aplikasi Pengunaan Visual Basic Pada Perhitungan Indeks Keandaan Pembangkit,” Elektron Jurnal Ilmiah, vol. 11, no. 2, pp. 63–68, 2019, https://doi.org/10.30630/eji.11.2.127.

A. Cekum, Junaidi, and Purwoharjono, “Studi Keandalan Pembangkit Listrik Tenaga Diesel (PLTD) Sukaharja Kabupaten Ketapang,” Jurnal Teknik Elektro Universitas Tanjungpura, vol. 2, no. 1, pp. 1–10, 2019, https://jurnal.untan.ac.id/index.php/jteuntan/article/view/34966.

M. S. Alvarez-Alvarado and D. Jayaweera, “Aging Reliability Model for Generation Adequacy,” 2018 IEEE International Conference on Probabilistic Methods Applied to Power Systems (PMAPS), pp. 1-6, 2018, https://doi.org/10.1109/PMAPS.2018.8440529.

A. N. Widiastuti, Sarjiya, K. A. Pinanditho, and E. T. Prastyo, “Evaluasi Keandalan Perencanaan Pembangkit Wilayah Jawa-Bali dengan Mempertimbangkan Ketidakpastian Peramalan Beban,” Jurnal Nasional Teknik Elektro Dan Teknologi Informasi, vol. 6, no. 2, pp. 230–234, 2017, https://journal.ugm.ac.id/v3/JNTETI/article/view/2861.

P. F. Ferdinant, L. Nurdiana, and A. Irman, “Evaluation of Power Plant Reliability Using Index Loss of Load in the Suralaya Power Plant,” in IOP Conference Series: Materials Science and Engineering, vol. 909, no. 1, pp. 1–9, 2020, https://doi.org/10.1088/1757-899X/909/1/012070.

G. Slipac, M. Zeljko, and D. Šljivac, “Importance of Reliability Criterion in Power System Expansion planning,” Energies, vol. 12, no. 9, pp. 1–18, 2019, https://doi.org/10.3390/en12091714.

I. Apriliyanto, E. D. Malia, A. R. Uspa, A. D. Bhaswara, and F. Rahman, “Studi Analisa Keandalan Pada Pembangkit Listrik Tenaga Uap (PLTU) Embalut Kalimantan Timur Menggunakan Perhitungan LOLP (Loss of Load Probabilty) dan LOLE (Loss of Load Expectation),” PoliGrid, vol. 3, no. 2, pp. 52–56, 2022, https://doi.org/10.46964/poligrid.v3i2.1706.

L. T. Al-Bahrani, W. Saaed, and M. Al-Kaabi, “Generation Reliability Enhancement based on Reliability Indices,” Journal of Physics: Conference Series, vol. 1844, no. 1, pp. 1–10, 2021, https://doi.org/10.1088/1742-6596/1844/1/012010.

A. Hidayati, Supriyatna, and A. B. Muljono, “Analisis Kontingensi terhadap Unjuk Kerja dan Keandalan Komposit Pembangkit dan Transmisi pada Sistem Kelistrikan Lombok,” Jurnal Dielektrika, vol. 3, no. 2, pp. 95–104, 2016, http://dielektrika.unram.ac.id/index.php/dielektrika/article/view/143.

I. S. Qamber, “Loss of Load Expectation Calculation for Power Plant,” IET Conference Publications, vol. 2019, no. CP758, 2019, https://doi.org/10.1049/cp.2019.0213.

U. Albab and D. Y. Sukma, “Upaya Peningkatan Indeks Keandalan Sistem Pembangkit dengan Peningkatan Kapasitas Sistem Pembangkit,” Jurnal Online Mahasiswa Fakultas Teknik, vol. 6, no. 2, pp. 1–6, 2019, https://jnse.ejournal.unri.ac.id/index.php/JOMFTEKNIK/article/view/25738.

R. Syahputra, F. Noor, and F. Mujaahid, “Analisis Indeks Keandalan Pembangkit Listrik Tenaga Hibrid Angin-Surya Menggunakan Metode EENS,” Semesta Teknika, vol. 23, no. 1, pp. 92–105, 2020, https://journal.umy.ac.id/index.php/st/article/view/9602.

R. A. Putra and I. T. Yuniahastuti, “Perhitungan Keandalan Pembangkit Loss of Load Probability (LOLP) untuk N Pembangkit,” Jurnal Electra, vol. 1, no. 2, pp. 13–19, 2021, https://doi.org/10.25273/electra.v1i2.8960.

R. A. Putra, I. T. Yuniahastuti, and R. D. Laksono, “Skenario Perbaikan Nilai Keandalan Loss of Load Probability pada PLTH Pantai Baru Pandansimo,” Jurnal Electra, vol. 2, no. 1, pp. 16–22, 2021, https://doi.org/10.25273/electra.v2i1.10500.

R. D. Laksono, I. T. Yuniahastusi, and A. P. P. Prakoso, “Skenario Peningkatan Keandalan Sistem Pembangkit Tenaga Listrik di Wilayah Bali Berdasarkan LOLP,” Jurnal Electra, vol. 2, no. 1, pp. 39–45, 2021, https://doi.org/10.25273/electra.v2i1.10525.

R. R. Dharmawan and U. T. Kartini, “Analisis Indeks Keandalan PLTGU Blok 1 PT. PJB UP Gresik Menggunakan Perhitungan Teorema Bayes dan Decomposisi LU,” Jurnal Teknik Elektro, vol. 9, no. 3, pp. 658–665, 2020, https://jurnalmahasiswa.unesa.ac.id/index.php/16/article/view/35589.

Syahrial, K. Sawitri, and P. Gemahapsari, “Studi Keandalan Ketersediaan Daya Pembangkit Listrik Pada Jaringan Daerah X,” Jurnal Elkomika, vol. 5, no. 1, pp. 93–105, 2017, https://doi.org/10.26760/elkomika.v5i1.93.

A. Tanjung, A. Jaya, S. Suryanto, and Apollo, “Evaluasi Keandalan PLTA Bakaru,” Sinergi, vol. 19, no. 1, pp. 80–87, 2021, https://doi.org/10.31963/sinergi.v19i1.2762.

Adriwiyono and B. P. Ichtiarto, “Analisa Kinerja Pembangkit Turbin Gas PT PJB Unit Pembangkit Muara Tawar Menggunakan Generating Availability Data System,” Operatoins Excellence, vol. 10, no. 3, pp. 304–320, 2018, https://doi.org/10.22441/oe.v10.3.2018.010.

A. Burhandono and N. Sinaga, “Menjaga Keandalan Sistem PLTS dengan Metode Failure Mode Effect Analysis (FMEA),” Jurnal Teknik Industri, vol. 12, no. 1, pp. 30–39, 2022, https://trijurnal.trisakti.ac.id/index.php/tekin/article/view/13958.

F. Anwar, “Usulan Perhitungan dan Perbaikan Tingkat Keandalan Desalination Plant PLTGU Muara Tawar dengan Menggunakan Weibull Analisis dan FMEA sebagai Dasar Skala Prioritas Pengoperasian,” Jurnal PASTI, vol. VIII, no. 2, pp. 171–190, 2014, https://www.neliti.com/publications/182877/usulan-perhitungan-dan-perbaikan-tingkat-keandalan-desalination-plant-pltgu-muar.

Adrianti, “Evaluasi Keandalan Pembangkit Listrik Tenaga Surya yang Terhubung ke Grid,” Jurnal Nasional Teknik Elektro, vol. 5, no. 2, pp. 230–236, 2016, https://doi.org/10.20449/jnte.v5i2.281.

H. D. Armono, D. K. Nugroho, and Mukhtasor, “Monte Carlo Simulation for Reliability Hydraulic Stability of Rubble Mound Breakwater Armour at Sudimoro Power Plant, Pacitan,” IOP Conference Series: Earth and Environmental Science, vol. 698, no. 1, 2021, https://doi.org/10.1088/1755-1315/698/1/012031.

I. Pamungkas, H. T. Irawan, Arhami, and M. Dirhamsyah, “Simulasi Monte Carlo untuk Menentukan Keandalan pada Bagian Boiler di Pembangkit Listrik Berbasis Batubara,” Jurnal Optimalisasi, vol. 4, no. 2, pp. 83–96, 2018, http://jurnal.utu.ac.id/joptimalisasi/article/view/1505.

A. N. Abdalla et al., “Metaheuristic Searching Genetic Algorithm Based Reliability Assessment of Hybrid Power Generation System,” Energy Exploration and Exploitation, vol. 39, no. 1, pp. 488–501, 2021, https://doi.org/10.1177/0144598720959749.

M. Cepin, Assessment of Power System Reliability. London: Springer, 2011, https://doi.org/10.1007/978-0-85729-688-7.

R. Billinton and R. N. Allan, Reliability Evaluation of Power Systems, 2 ed. New York: Plenum Press, 1996, https://doi.org/10.1007/978-1-4899-1860-4.

A. A. Chowdhury and D. O. Koval, Power Distribution System Reliability. New Jersey: John Wiley & Sons, Inc, 2009, https://doi.org/10.1002/9780470459355.

Menteri ESDM RI, Rencana Usaha Penyediaan Tenaga Listrik PT. PLN (Persero) 2019-2028. Indonesia, 2019.

Downloads

Published

2023-02-04

How to Cite

[1]
I. Alfi and R. F. . Kusmayana, “Visual Studio Application for Generation Power System Reliability Calculations ”, Buletin Ilmiah Sarjana Teknik Elektro, vol. 5, no. 1, pp. 56–66, Feb. 2023.